The first step in the relining of pipes in Rubtsovsk will be completed by the end of the summer

© RIA Novosti / Vitaly to Incomerate in fotoracconti pipes. ArchiveThe first step in the relining of pipes in Rubtsovsk will be completed by the end of the summer© RIA Novosti / Vitaly to Uncovereth the image Bank

The completion of the first phase of the project on modernization of heat supply in Rubtsovsk, Altai territory is transferred to the end of the summer, is spoken in the message of Siberian generating company (SGK).

The first phase of the project is building bridges between the contours of the Rubtsovskaya TETS and the southern thermal station with a length of 2.3 kilometers were to be completed by the end of may. Now completed 75% of the work. The reason for the delay was the large amount of groundwater in this spring and worn out heating.

«The backlog is due to the fact that the ground water this year has risen unexpectedly high. Add subjective factors: the network, both thermal and water utility, so worn, that is constantly flowing… In any case, the construction and relining of pipelines will be completed by the end of the summer…» — are words in the message CEO SGK Mikhail Kuznetsov.

The company is engaged in heat supply. on the basis of the rent of the thermal complex from August 2016. At the moment, other enterprises, responsible for the heat supply of the city, are in the bankruptcy stage.

The volume of investments in modernization of heat supply of Rubtsovsk is 1.5 billion rubles of direct investments and another half a billion is envisaged for the compensation of losses of the enterprise. To recover the funds in the company for 12-15 years.