The builders started the construction of the bodies of the most powerful supports of the Seine estuary road and rail bridge across the Kerch Strait, which will be joined in the only place in the area of the Seine estuary part, said Wednesday the information center «Crimean bridge».

The construction of the bodies of the Seine estuary supports (which will be installed the stairs) goes to the construction of the bridge, they are different for road and railway parts: reinforced concrete under the highway and the steel frame under the railway. Such differences are due to different design loads on the supports that will take on arch spans, the press service reported.

«Seine estuary supports in the project two — No. 252 (close to Taman) and No. 253 (near Kerch). This is the only area where the linings of both bridges combined grillage (jumper — ed). For the rest of the highway road and rail bridges are separately», — said the builders.

Best viewing angles #стройкавека360 —
on Tuesdays ? #demost #metromost https://t.co/iDT05fZwWq

Crimean bridge (@Krymsky_bridge) 30 may 2017

The creation of pile foundations on these legs ended in April, and then began work on the raft. Gratings on the road part fully implemented. For this work took about 2.8 thousand tons of rebar and more than 5.5 thousand cubic meters of concrete.

The construction of the pile caps in the rail part of the supports are made partially on the first, lower, layer. To be followed by reinforcement and concreting of pile cap in parallel with installation of the main power elements of bodies supports — steel cores. As a result of a 25-foot structure weighing about 330 tons each form the steel frames of the bodies of the supports. Then they will «dress» armokarkasa and tabaconist.

At the same time on the raft Seine estuary supports the creation of special support structures that will be involved in the installation of arch spans. Installation of two arched spans of the bridge is scheduled for the end of August 2017.

The bridge across the Kerch Strait that will link Crimea and Krasnodar Krai, will be the longest in Russia — its length is 19 kilometers. The total cost of the project is 227,92 billion. The beginning of the movement of vehicles on the bridge is scheduled for December 2018.

Read more about news of the Crimea — on crimea.ria.ru >>

Two bridges across the Kerch Strait will connect in the center of the fairwayWhat is the bridge across the Kerch Strait

Source

Be the first to comment on "Two bridges across the Kerch Strait will connect in the center of the fairway"

Leave a comment

Your email address will not be published.


*