Energy has completed emergency repair work in North Ossetia

© RIA Novosti / Marina to Listenability in fotobankaEnergy has completed emergency repair work in North Ossetia© RIA Novosti / Marina to Listenability the image Bank

Electricity consumers affected by heavy rains in North Ossetia, restored in full, according to the PJSC «IDGC of the North Caucasus».

According to the company, the nine pillars of power lines were washed away by torrential rains. As a result of incident without electricity there were more than seven thousand people in Aldanskom district and less than two thousand in IrAF district of the Republic.

«Abnormally-recovery work in North Ossetia, the specialists of «IDGC of the North Caucasus» is fully completed. The power supply of all consumers is carried out in full», — stated in the message.

It is noted that energy drinks were introduced a special mode of operation.

«Recovery works organised by the power grid company, involved 11 teams, 30 people from 17 units in the affected areas were directed to a backup power supply for 30 kW each. Before noon about 5 thousand consumers energy powered on a temporary basis,» said the company.