Avtodor said the reasons for the postponement of the delivery route M11

© RIA Novosti / Vitaly to Belowaverage in photobacteria Moscow — Saint Petersburg. Archival photoAvtodor said the reasons for the postponement of the delivery route M11© RIA Novosti / Vitaly to Belowaverage the image Bank

The postponement of the commissioning of the entire high-speed toll highway Moscow-Saint Petersburg in 2019 is associated with the presence of objects of the early iron age on the 663-kilometer road under construction, should be the message of the state company «Avtodor», implementing the project.

According to «Avtodor», on the site of excavations have found more than 400 economic and pole holes in them — fragments of ceramic vessels of hatched ceramics, quartz flakes and a fragment of a grinding axe, several pockets, as well as traces of Slavic colonization of the area around the XIV-XV centuries – the characteristic of the Slavs ceramic vessels, spindles, knives, jewelry.

«When research and rescue archaeological field work on the «Settlement Voyskorovo» is completed, the culture Committee will remove the requirement to suspend work and the contractor will continue the construction of the road. But the completion of the 7th and 8th sections of the route M11 will have to move at a later time,» explains the company.Avtodor said the reasons for the postponement of the delivery route M11© Infografiken roads of Russia

Source